PROJECT: CHILDS WAY CIVIL AND MECHANICAL UTILITIES UPGRADE

The Childs Way Civil and Mechanical Utilities Upgrade project involved upgrading both the domestic and fire water lines and steam lines, and adding new reclaimed water lines and chilled water lines from Watt Way to McClintock on Childs Way. It included the re-piping of two underground steam vaults and building a new underground steam vault with new piping. According to Jennifer Schlesinger, FMS Engineering Department Project Manager, the schedule proved to be challenging since the entire project needed to be completed in a month and a half to prepare for the installation of a new hardscape before the start of the Fall semester.